Ada County Highway District

Stroebel Road Bridge #236

General Description:

Project Update as of 4/10/17:  Footings on Stroebel are complete. One half of the footings on Locust Grove are complete. Crews are placing bridge structures on both bridges this week.

Project Purpose:  In February 2017, ACHD will replace the Locust Grove Bridge #330 A, as well as the Stroebel Bridge #236, both of which are located just south of E. Kuna Road. The replacement of these bridges is necessary due to spalling concrete. Both bridges will be constructed one half at a time, allowing vehicles to cross the bridges in one direction at a time. Construction is expected to be complete by May 2017.

Locust Grove Bridge #330A

 

Design:
FY2015
Right-of-Way:
FY2016
Construction:
February 2017

Time Frame

Start Date:
February 2017
End Date:
May 2017

Return to Projects

Project Manager


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster