Ada County Highway District

Eagle Road Bridge #1029 (Eagle)

Project Update as of 9/15/17:  The bridge has been removed and excavation is complete. Crews are working on placing blocks.

General Description:

  • Replace existing bridge on Eagle Road, located 1/4 mile north of Floating Feather over Dry Creek.
  • New bridge will have two travel lanes, wide shoulders and sidewalk.
  • The contractor may close Eagle Road at the bridge for approximately 6 weeks during construction.
  • At all other times, two lanes will be maintained on Eagle Road between Floating Feather Road and Beacon Light Road, however there may be temporary lane restrictions with flaggers.
  • Other impacts include general construction noise, dust, equipment back up alarms and ground vibration.

 

 Eagle Road Bridge East 

 

Time Frame

Start Date:  Construction Summer 2017
End Date:  Fall 2017

Return to Projects

Project Manager


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017