4th Street Bridge #1291 (Kuna)

General Description:

This project is substantially complete as of 4/6/17.

Project Description

  • The bridge over the canal on 4th Street will be replaced due to deterioration. The new bridge will be extended to connect to the existing bridge nearby on Kay Street. Sidewalk will be added on 4th Street to run east over the new bridge and connect to the existing sidewalk on Kay Street. Pedestrian ramp improvements will be added to the southwest corner.
Design:
FY2015
Right-of-Way:
FY2016
Construction:
2017

Time Frame

Start Date:
February 2017
End Date:
Mid-April 2017

Return to Projects

Project Manager

Brian McCarthy
projects@achdidaho.org